Matches in DBpedia 2016-04 for { <http://dbpedia.org/resource/Colíder_Dam> ?p ?o }
- Colíder_Dam length "1.526".
- Colíder_Dam abstract "The Colíder Dam is a rock-fill dam with an asphalt-concrete core, currently under construction on the Teles Pires river about 40 km (25 mi) southeast of Colíder in the state of Mato Grosso, Brazil. The dam's hydroelectric power stations will have 3 turbines each 115 MW resulting in a total installed capacity of 306.9 MW. Construction on the run-of-the-river type station was initiated in May 2011, and is expected to be operational in 2015.The dam is part of a planned six power plant \"Hidrovia Tapajos/Teles Pires\" project to create a navigable waterway connecting the interior of Brazil to the Atlantic Ocean. The waterway will consist of five dams on the Teles Pires river (53 megawatts (71,000 hp) Magessi Dam, 430 megawatts (580,000 hp) Sinop Dam, 342 megawatts (459,000 hp) Colíder Dam, 1,820 megawatts (2,440,000 hp) Teles Pires Dam, 746 megawatts (1,000,000 hp) Sao Manoel Dam) and the 230 megawatts (310,000 hp) Foz do Apiacas Dam on the Apiacas river.The Colíder Dam and the Teles Pires Dam are currently under construction, while the smaller upstream dams are still in the planning stages.".
- Colíder_Dam buildingStartDate "May 15, 2011".
- Colíder_Dam buildingStartYear "2011".
- Colíder_Dam description "Embankment, concrete gravity composite".
- Colíder_Dam height "40.0".
- Colíder_Dam lake Colíder_Dam__1.
- Colíder_Dam length "1526.0".
- Colíder_Dam location Colíder.
- Colíder_Dam location Mato_Grosso.
- Colíder_Dam openingYear "2015".
- Colíder_Dam operator Copel.
- Colíder_Dam part Colíder_Dam__2.
- Colíder_Dam purpose "Power".
- Colíder_Dam river Teles_Pires.
- Colíder_Dam status "Under construction".
- Colíder_Dam volume "4961000.0".
- Colíder_Dam wikiPageExternalLink uhecolider.
- Colíder_Dam wikiPageID "44903845".
- Colíder_Dam wikiPageLength "4686".
- Colíder_Dam wikiPageOutDegree "21".
- Colíder_Dam wikiPageRevisionID "705543659".
- Colíder_Dam wikiPageWikiLink Category:Dams_in_Mato_Grosso.
- Colíder_Dam wikiPageWikiLink Category:Dams_under_construction.
- Colíder_Dam wikiPageWikiLink Category:Hydroelectric_power_stations_in_Brazil.
- Colíder_Dam wikiPageWikiLink Category:Rock-filled_dams.
- Colíder_Dam wikiPageWikiLink Category:Run-of-the-river_power_stations.
- Colíder_Dam wikiPageWikiLink Colíder.
- Colíder_Dam wikiPageWikiLink Copel.
- Colíder_Dam wikiPageWikiLink Dam.
- Colíder_Dam wikiPageWikiLink Kaplan_turbine.
- Colíder_Dam wikiPageWikiLink List_of_power_stations_in_Brazil.
- Colíder_Dam wikiPageWikiLink Mato_Grosso.
- Colíder_Dam wikiPageWikiLink Run-of-the-river_hydroelectricity.
- Colíder_Dam wikiPageWikiLink Teles_Pires.
- Colíder_Dam wikiPageWikiLink Teles_Pires_Dam.
- Colíder_Dam wikiPageWikiLink Watt.
- Colíder_Dam wikiPageWikiLinkText "Colíder Dam".
- Colíder_Dam constructionBegan "2011-05-15".
- Colíder_Dam coordinatesDisplay "inline,title".
- Colíder_Dam coordinatesType "type:landmark".
- Colíder_Dam cost "1.0E9".
- Colíder_Dam damCrosses "Teles Pires river".
- Colíder_Dam damType "Embankment, concrete gravity composite".
- Colíder_Dam imageCaption "Site of the Colíder Dam".
- Colíder_Dam latD "10".
- Colíder_Dam latM "59".
- Colíder_Dam latNs "S".
- Colíder_Dam latS "6.6".
- Colíder_Dam location "Colíder, Mato Grosso, Brazil".
- Colíder_Dam locationMap "Brazil".
- Colíder_Dam locationMapCaption "Location of the Colíder Dam in Brazil".
- Colíder_Dam longD "55".
- Colíder_Dam longEw "W".
- Colíder_Dam longM "46".
- Colíder_Dam longS "30.39".
- Colíder_Dam name "Colíder Dam".
- Colíder_Dam nameOfficial "Usina Hidrelétrica Colíder".
- Colíder_Dam opening "2015".
- Colíder_Dam operator Copel.
- Colíder_Dam plantCapacity "306.9".
- Colíder_Dam plantCommission "2015".
- Colíder_Dam plantOperator "Companhia Paranaense de Energia - COPEL".
- Colíder_Dam plantTurbines "3".
- Colíder_Dam plantType Run-of-the-river_hydroelectricity.
- Colíder_Dam purpose "Power".
- Colíder_Dam spillwayType "Overflow, 1 controlled gates".
- Colíder_Dam status "Under construction".
- Colíder_Dam website uhecolider.
- Colíder_Dam wikiPageUsesTemplate Template:Convert.
- Colíder_Dam wikiPageUsesTemplate Template:Infobox_dam.
- Colíder_Dam wikiPageUsesTemplate Template:Reflist.
- Colíder_Dam wikiPageUsesTemplate Template:Use_dmy_dates.
- Colíder_Dam subject Category:Dams_in_Mato_Grosso.
- Colíder_Dam subject Category:Dams_under_construction.
- Colíder_Dam subject Category:Hydroelectric_power_stations_in_Brazil.
- Colíder_Dam subject Category:Rock-filled_dams.
- Colíder_Dam subject Category:Run-of-the-river_power_stations.
- Colíder_Dam hypernym Dam.
- Colíder_Dam point "-10.985166666666666 -55.775108333333336".
- Colíder_Dam type ArchitecturalStructure.
- Colíder_Dam type Dam.
- Colíder_Dam type Infrastructure.
- Colíder_Dam type Place.
- Colíder_Dam type Location.
- Colíder_Dam type Place.
- Colíder_Dam type Thing.
- Colíder_Dam type SpatialThing.
- Colíder_Dam type Q12323.
- Colíder_Dam comment "The Colíder Dam is a rock-fill dam with an asphalt-concrete core, currently under construction on the Teles Pires river about 40 km (25 mi) southeast of Colíder in the state of Mato Grosso, Brazil. The dam's hydroelectric power stations will have 3 turbines each 115 MW resulting in a total installed capacity of 306.9 MW.".
- Colíder_Dam label "Colíder Dam".
- Colíder_Dam sameAs Q19879781.
- Colíder_Dam sameAs m.012kxbfs.
- Colíder_Dam sameAs Q19879781.
- Colíder_Dam lat "-10.985166666666666".
- Colíder_Dam long "-55.775108333333336".
- Colíder_Dam wasDerivedFrom Colíder_Dam?oldid=705543659.
- Colíder_Dam homepage uhecolider.
- Colíder_Dam isPrimaryTopicOf Colíder_Dam.
- Colíder_Dam name "Colíder Dam".