Matches in DBpedia 2015-10 for { ?s ?p "The Kazunogawa Dam (葛野川ダム) uses water from the Sagami River system to power a 1,200 MW pumped storage hydroelectric scheme. It is located 18 kilometres (11 mi) east of Kōshū in Yamanashi Prefecture, Japan. The station is designed to have an installed capacity of 1,600 megawatts (2,100,000 hp) and three of the four 400 megawatts (540,000 hp) generators are currently operational. Construction on the power station began in 1993 and the first generator was commissioned on 3 December 1999. The second was commissioned on 8 June 2000. The third on become operational on 9 June 2014, six year early due to post-power demand from the Great East Japan earthquake. The fourth and final generator is slate to be commissioned by 2024. It is owned by TEPCO and was constructed at a cost of $2.2 billion USD."@en }